Benefits:
- Energy savings delivered = 2.2m kWhr/pa
- Energy cost savings = S$347,000
- Emissions reduction = 985 te CO2
- Simple pay back = 1.3 years
- Further energy savings identified = 2.5m kWhr/pa
Facility: Pharma Manufacturing & laboratories
Issue: Very high energy demand driven by original HVAC design & layout
Brief: Reduce energy demand without compromising on Compliance or Laboratory safety
Solution:
- Reduce existing air change rates
- Reduce existing fresh air volume
- Improve plant operational maintenance
- Optimise BMS system
- Recommended upgrading laboratory fume cupboards to VAV
- Recommended upgrade & control of warehousing Facilities
Conclusion: EECO2 supported HVAC design review, project scoped out & managed local test & balance & BMS Contractors to complete project – project successfully completed also produced a prioritised Action Plan to implement further savings